The geotechnical investigation
What is a geotechnical investigation for, and when should it be commissioned?
It establishes what the ground can carry. It lets the designer choose the type of foundation, its depth and its sizing, or define a pavement structure. Without it, sizing rests on assumptions: either oversized, and therefore needlessly expensive, or undersized, and therefore dangerous. Commission it as early as possible, before the drawings are finalised — an investigation carried out after design often forces the sizing to be reworked, and sometimes the siting of the building itself.
Is it mandatory in Cameroon?
Soil and construction materials quality control and geotechnical investigation are governed by Law No. 99/017 of 22 December 1999, and may only be carried out by laboratories accredited by the Ministry of Public Works (MINTP). Public contracts and donor-funded projects require it as a matter of course. For a private project it remains strongly advisable: it is the cheapest item in the budget and the one that protects every other.
What does the report contain?
Borehole logs, test results referenced to their standard, classification of the soils encountered, the allowable bearing pressure adopted, the interpretation, the conclusions, and recommendations the designer can act on.
Inspection during construction
What is the difference between geotechnical investigation and geotechnical inspection?
The investigation happens before the works: it tells you about the ground so you can design. Inspection happens during the works: it verifies that what is being built matches the specification — compaction, bearing capacity, concrete strength, materials quality.
What happens if something fails to comply?
It is reported at once to the works supervisor and the project owner, in writing, with the test result attached. An inspection laboratory that does not raise the alarm is not doing its job.
Do you work outside Yaoundé?
Yes. We mobilise teams nationwide and, where needed, set up a site laboratory on the works. Our consultants have worked in all ten regions of Cameroon, as well as in Gabon, the Central African Republic, Chad and Equatorial Guinea.
Concrete and materials
How is concrete strength verified?
By casting 16×32 cylindrical specimens during the pour, curing them under standard conditions, then crushing them at 7 and 28 days to NF EN 12390-3. It is the only method that yields a legally defensible figure.
And for a structure already built?
Two non-destructive methods: the rebound hammer, which estimates surface strength of hardened concrete (NF EN 12504-2), and the cover meter, which locates reinforcement and measures concrete cover (NF EN 12504-1). Coring followed by a laboratory test gives a more precise figure where the stakes justify it.
Working with us
Are you accredited?
Yes. TECH-ECF is accredited as a Category C private laboratory by the Ministry of Public Works (MINTP) — Arrêté N° 010/A-C/MINTP/CAB du 03/04/2023 (Ministerial Order) — for groups I (soils and foundations), II (aggregates) and III (hydraulic binders, concrete, mortars, concrete blocks, bricks, roof tiles and ceramic products).
Is your equipment calibrated?
Yes. Inspection, measuring and test equipment is calibrated and verified by LABOGENIE, the national civil engineering laboratory, in accordance with circular letter No. 5280/CAB/MINTP of 1 July 2019.
Can you supply the documents for a tender?
Yes. On request we send the current administrative file: a copy of the accreditation, social security and tax compliance certificates, the registration certificate, the insurance policy, the articles of association, staff CVs, the equipment list and calibration certificates. We also work regularly in consortium with national and international consulting firms.
How do I obtain a quote, and how long does the work take?
Send us the nature of the structure, its location, its scale — number of storeys or length — and the outline programme, by email or by telephone. We come back to you with a proposal. Timing depends on the scale of the investigation programme and the location; some tests set their own pace, since 28-day concrete strength cannot be known before 28 days have passed. The programme is stated in the proposal.